Show the governing municipality the wall’s full footprint, grade change and nearby loads before relying on a permit exemption. A fence or an old wall is not proof of where the lot line lies. Use a boundary survey for that question, and ask whether the permit office also needs elevations, a cross section or drawings signed by a professional.

Separate the property lines from the grading information

Start with the survey, then put the wall, its ends, the expected work limits and the outlet on a drawing. Ask for existing and proposed grades on both sides, and label which heights are measured and which are proposed. Wilmette’s permit submittal guidance says that when a plat is required, it must be a boundary plat reflecting current conditions and accurately showing easements. Its site grading requirements call for top and bottom wall elevations on applicable plans, and signed and sealed structural calculations for walls over 3 feet. Its engineering permit resources separately address grading, drainage and work in the public right-of-way. Ask Wilmette how it classifies your exact scope rather than inferring a wall exemption from a general list.

Use the rule for your address, not the nearest example

For Chicago, Section 14A-4-402.1 lists a retaining-wall permit exemption only where the wall is no higher than 4 feet from footing bottom to wall top, does not support a surcharge and does not hold back liquid. The measurement is not just the part you see above ground. Separately, the section states that work affecting the exterior or designated interior elements of a Chicago Landmark requires a permit. Naperville’s 2022 residential permit guide lists building or replacing a retaining wall over 3 feet as permit work, but the city uses a newer code set for plans submitted on or after April 1, 2026. Ask Naperville to confirm the current rule, how it measures height and which grading or drawing requirements apply. Neither city’s rule determines what your wall can safely support.

Ask who will confirm each outstanding item

Record who gets the permit determination, who provides the applicable survey or drawings, and who arranges utility locates before excavation. Illinois emergency management guidance distinguishes DIGGER inside Chicago from JULIE outside Chicago. Keep the locate step separate from the boundary survey and ask the project team how it will identify any private facilities. If the permit office needs to understand what the wall supports, send the slope and load sketch. Put the resulting assignments into the written proposal so they do not fall between the homeowner, designer and installer.